In MultiQuant™ software, an arrow can be added to the peak review chromatogram window to represent the expected retention time. To do this, right click within the peak review pane and select Options from the list. A Peak Review Options popup window will appear. Check the option Mark Expected RT with Arrow under the Appearance tab. Then select OK. 

User-added image

Once this option is selected, an arrow should show for expected retention time under the chromatogram. 